STUDENT ACCOMMODATION
Chancellors
Wharf - Student Accommodation Kitchen & Bathroom Refurbishment
• Spread over 3
Buildings
• 32
Bathrooms
• 3
Kitchens
• M&E
Services - Lighting; Power; Fire Alarm; Ventilation;
Heating; Domestic Services & Sanitaryware
• Completed
in the short time frame of the summer holidays ready
for the new term
City Block
Lancaster New Build, Design And Build Student Accommodation
• Design
• M&E
installation
• CHP
• Lightning
protection
• Air
source
•
Project value £600,000
• Project
duration 24 weeks
Student
Accommodation Portsmouth
• Design and
installation of intelligent leak detection system
• Removal
and reinstatement of ceilings
• Builders
work in connection
• Phased
execution of works
• Mobile
monitoring alerts
•
Project value £160,000
•
Project duration 12 weeks
Replacement Of
Hot Water Cylinders To Student Accommodation
• Replacement
of water cylinders
• Builders
work in connection
•
Waste removal
• Remedial
works to bathrooms
• Full
recommission of hot water systems
•
Project value £60,000
•
Project duration 8 weeks
Electrical Testing
And Remedial
Works To Student Accommodation
• Electrical
testing to student accommodation
• Remedial
works to ensure safe compliance
•
Working in live environment
• Use of
mobile technology to ensure fast completion of
certification
•
Duration 20 weeks
•
Project value £200,000